Maryland NEVI Program Round 3
Round 3 Request for Proposals (RFP)
Round 3 of Maryland’s National Electric Vehicle Infrastructure (NEVI) Program opened for proposals on March 17, 2026. The Maryland Department of Transportation (MDOT) issued a press release for the announcement.
To ensure Maryland’s Alternative Fuel Corridors (AFCs) are built out most efficiently, proposed sites must be located within one of the nine designated Targets Areas.
Use the Utility Contact List to initiate utility service requests and pre‑applications for potential NEVI Round 3 sites. Make sure to also check out our Partnering Form for teaming and partnership opportunities.
Click the image below to view an interactive online map of the Round 3 Target Areas.
NEVI Round 3 Timeline
| Activity | Date |
|---|---|
| Request for Proposals (RFP) Released | March 17, 2026 |
| Virtual Pre-Proposal Conference | March 30, 2026 |
| Proposals Due | June 24, 2026 |
| MDOT Proposal Review | June-August 2026 |
| Conditional Award Notifications | August 2026 (Subject to Change) |
Maryland NEVI Program Round 2
NEVI Round 2 Conditional Awards
On October 28, 2025, the Maryland Department of Transportation (MDOT) issued a press release to announce conditional awards under Round 2 of the National Electric Vehicle Infrastructure (NEVI) Program. Conditional awards have been issued for 12 project sites in 12 counties within Maryland. These projects will use over $9.5 million in federal investments to install 48 public, convenient, and reliable Direct Current (DC) fast chargers along the state’s designated electric vehicle (EV) Alternative Fuel Corridors.

NEVI Round 2 Timeline
| Activity | Date |
|---|---|
| Request for Proposals (RFP) Released | December 17, 2024 |
| Virtual Pre-Proposal Conference | January 14, 2025 |
| Proposals Due (Extended) | August 27, 2025 |
| MDOT Proposal Review | September-October 2025 |
| Conditional Award Notifications | October 28, 2025 |
Maryland NEVI Program Round 1
NEVI Round 1 Awards
On July 10, 2024, Governor Wes Moore issued a press release to announce conditional awards under NEVI Program Round 1. Final awards have been issued for 19 project sites in 13 counties within Maryland. These projects will use nearly $9.5 million in federal investments to install 118 public, convenient, and reliable DC fast chargers along the state’s designated EV Alternative Fuel Corridors.

NEVI Round 1 Timeline
| Activity | Date |
|---|---|
| Request for Proposals (RFP) Released | January 16, 2024 |
| Virtual Pre-Proposal Conference | February 13, 2024 |
| Proposals Due | April 10, 2024 |
| MDOT Proposal Review | April-June 2024 |
| Conditional Award Notifications | July 10, 2024 |
Having issues with a NEVI charger? For the quickest resolution, please report charger outages and other issues to the charging station’s customer support. Contact information is located on the charging station and in the awards list below.