Maryland NEVI Program Round 3

NEVI Round 3 Conditional Awards

On August 18, 2026, the Maryland Department of Transportation (MDOT) issued a press release to announce conditional awards under Round 3 of the National Electric Vehicle Infrastructure (NEVI) Program. Conditional awards have been issued for 5 project sites in 5 counties within Maryland. These projects will use about $3.7 million in federal investments to install 24 public, convenient, and reliable Direct Current (DC) fast charging ports along the state’s designated electric vehicle (EV) Alternative Fuel Corridors.

An infographic view of the NEVI Round 3 Conditional Awards Map

NEVI Round 3 Timeline

Activity Date
Request for Proposals (RFP) Released March 17, 2026
Virtual Pre-Proposal Conference March 30, 2026
Proposals Due June 24, 2026
MDOT Proposal Review June-August 2026
Conditional Award Notifications August 12, 2026

Maryland NEVI Program Round 2

NEVI Round 2 Conditional Awards

On October 28, 2025, MDOT issued a press release to announce conditional awards under Round 2 of the NEVI Program. Conditional awards have been issued for 12 project sites in 12 counties within Maryland. These projects will use over $9.5 million in federal investments to install 48 public, convenient, and reliable Direct Current (DC) fast charging ports along the state’s designated EV Alternative Fuel Corridors.

NEVI Round 2 Timeline

Activity Date
Request for Proposals (RFP) Released December 17, 2024
Virtual Pre-Proposal Conference January 14, 2025
Proposals Due (Extended) August 27, 2025
MDOT Proposal Review September-October 2025
Conditional Award Notifications October 28, 2025

Maryland NEVI Program Round 1

NEVI Round 1 Awards

On July 10, 2024, Governor Wes Moore issued a press release to announce conditional awards under NEVI Program Round 1. Final awards have been issued for 15 project sites in 11 counties within Maryland. These projects will use nearly $6.5 million in federal investments to install 102 public, convenient, and reliable DC fast chargers along the state’s designated EV Alternative Fuel Corridors.

NEVI Round 1 Timeline

Activity Date
Request for Proposals (RFP) Released January 16, 2024
Virtual Pre-Proposal Conference February 13, 2024
Proposals Due April 10, 2024
MDOT Proposal Review April-June 2024
Conditional Award Notifications July 10, 2024

Having issues with a NEVI charger? For the quickest resolution, please report charger outages and other issues to the charging station’s customer support. Contact information is located on the charging station and in the awards list below.